Haryana Data Centre Policy 2026

Up to ₹25 Cr
Max CAPEX Support (Hyperscale DC)
Up to ₹8 Cr/Yr
Max OPEX Support (5 Years)
500% FAR
Relaxed Building Floor Area Ratio
100% Ceil
Max Combined Incentive Cap vs FCI
Share:
Overview & Vision

Haryana Data Centre Policy 2026 at a Glance

The Haryana Data Centre Policy 2026, notified by the Department of Industries & Commerce vide Notification No. 20/12/2026-4IB-1 on 27 May 2026, is a 5-year flagship framework designed to position Haryana as a globally competitive hub for digital infrastructure and cloud processing.

With India's data centre capacity expanding toward 2,100 MW by FY2027, Haryana leverages its strategic location in the National Capital Region (Gurugram and Faridabad), reliable dual-grid power infrastructure, extensive optical fibre networks, and proximity to international airports to target ₹10,000 Crore in cumulative investments.

The policy was approved by the Council of Ministers on 18 May 2026 with concurrence from the Finance Department (U.O. No. 1/27/2026-3FD-III//2026/7008). It remains valid for 5 years from 27 May 2026.

Core Policy Objectives — Clause 4

  • Attract ₹10,000 Crore of cumulative investment in the data centre ecosystem during the policy period.
  • Provide transparent, time-bound Single Roof clearances via the Haryana Enterprise Promotion Board (HEPB).
  • Promote green data centres through adoption of renewable energy and water-efficient cooling systems.
  • Drive allied tech growth in AI, fintech, cloud services, and digital public infrastructure.
  • Generate high-quality direct and indirect employment across engineering, IT, construction, and facility management.
1. Definitions & Categorization

Categorization and Minimum Eligibility Gates

To qualify under this policy, Data Centres and Data Centre Parks must be established within Haryana and meet contracted power capacity thresholds dedicated to data centre operations:

Table 1 — Data Centre Category Classification (Clause 2.1)

CategoryContracted Power CapacityPolicy Eligibility Gate
Hyperscale Data CentreExceeding 10 MWEligible under Policy Clause 9.1
Core Data CentreMore than 1 MW and up to 10 MWEligible under Policy Clause 9.1
Edge Data Centre300 kW up to 1 MWCovered under Haryana MSME Policy 2026
Data Centre ParkMinimum 20 MW cumulative powerEligible under Policy Clause 10.1

Key Operational Definitions (Clauses 2.4 - 2.15)

TermDefinition & Thresholds
Fixed Capital Investment (FCI)New investment in land, building, IT/Non-IT equipment, power backup, and captive RE plants made before COD and within 1 yr (MSME/Large) or 3 yrs (Mega/Ultra-Mega).
New Enterprise / UnitUnit commencing operations during the policy period. Expansions at different locations are treated as New Units.
Expansion / DiversificationExisting unit undertaking at least 50% additional FCI, OR 25% additional FCI with min ₹125 Cr, OR exceeding Mega/Ultra Mega location thresholds.
Local EmployeeBona fide resident of Haryana verified exclusively via Parivar Pehchan Patra (PPP).
Net SGSTSGST paid through cash ledger after first exhausting all available Input Tax Credit (ITC), including IGST ITC.
Data Centre Park DeveloperEntity developing an integrated cluster of 2+ DC units over planned infrastructure (roads, power, connectivity, water, drainage) per TCP norms.
2. Fiscal Incentives for DC Units

CAPEX, OPEX & Employment Subsidies for Data Centre Units

A. Capital Expenditure (CAPEX) Support — Clause 9.1(A)

Reimbursement of eligible capital expenditure (ECE) disbursed in 10 equal annual instalments starting after commencement of commercial operations or achievement of committed investment:

DC Unit CategoryCAPEX Reimbursement PercentageMaximum Incentive Ceiling
Hyperscale Data Centre (>10 MW)20% of Eligible Capital Expenditure (ECE)₹25 Crore per unit
Core Data Centre (1 MW – 10 MW)10% of Eligible Capital Expenditure (ECE)₹1 Crore per MW
Edge Data Centre (300 kW – 1 MW)Provided under Haryana MSME & Exports PolicyAs per MSME Policy 2026
Eligible CAPEX includes building construction, IT & Non-IT machinery, captive RE (>100 kW), ETP/STP, DSIR-recognized R&D centers, stamp duty on land lease, External Development Charges (EDC), cooling tech expenses, and Green Building certification fees (LEED, IGBC, GRIHA, BEE).

B. Operational Expenditure (OPEX) Support — Clause 9.1(B)

Reimbursement of eligible operational costs for a period of 5 years from date of commencement of commercial operations:

DC Unit CategoryOPEX Reimbursement PercentageAnnual Incentive Ceiling
Hyperscale Data Centre (>10 MW)50% of eligible operational expenditure₹8 Crore per annum
Core Data Centre (1 MW – 10 MW)30% of eligible operational expenditure₹4 Crore per annum

Eligible OPEX heads include: Net SGST paid to GoH, wheeling and transmission charges paid for power import, electricity duty paid to GoH, and expenses incurred for global data centre certifications.

C. Local Employment Generation Subsidy — Clause 9.1(C)

Granted for 10 years from COD to reward high-quality local hiring verified via Parivar Pehchan Patra (PPP):

Haryana Local Workforce ProportionGeneral Category Subsidy RateWomen / SC / Divyang / Agniveer / Ex-Servicemen Subsidy Rate
< 15% Local EmployeesNot ApplicableNot Applicable
≥ 15% Local Employees100% + {20% * (% Local - 15%)} of gross monthly salary (Cap: ₹1 Lakh/yr/emp)120% + {20% * (% Local - 15%)} of gross monthly salary (Cap: ₹1.2 Lakh/yr/emp)
If the average gross monthly salary of an eligible Haryana local employee is below ₹48,000, a minimum employment subsidy of ₹48,000 per annum is guaranteed.

D. HKRN Employment Booster (EPF Support)

  • Employer EPF Reimbursement: 100% reimbursement on employer's statutory EPF contribution for 5 years for hires made through Haryana Kaushal Rozgar Nigam (HKRN), capped at 12% of basic+DA or ₹25,000/yr/employee.
  • Employee EPF Reimbursement: 100% employee EPF contribution reimbursed directly to HKRN-recruited workers via Direct Benefit Transfer (DBT) for 5 years (capped at ₹25,000/yr/employee).
  • HEPB Customized Packages: Ultra Mega and Mega Projects are eligible for customized incentive packages approved by the Haryana Enterprise Promotion Board (HEPB) over and above standard policy heads.
3. Incentives for DC Parks

Support Offered to Data Centre Park Developers

A. Park CAPEX Support — Clause 10.1(A)

Data Centre Park Developers (minimum 20 MW cumulative contracted power) receive 20% CAPEX reimbursement on park infrastructure, subject to a ceiling of ₹15 Crore, disbursed in 4 tranches:

Instalment TrancheDisbursement PercentageEligibility Milestone Criteria
1st Instalment50% of Eligible IncentiveGrant of license & completion of basic amenities by TCP Department
2nd Instalment20% of Eligible IncentiveProof of operation of at least 25% of total permissible unit area
3rd Instalment15% of Eligible IncentiveProof of operation of at least 50% of total permissible unit area
4th Instalment15% of Eligible IncentiveProof of operation of at least 75% of total permissible unit area

B. Park Interest Rate Subsidy

Developers are entitled to an Interest Rate Subsidy @ 5% on term loans for 5 years, subject to an annual ceiling of ₹5 Crore per annum.

4. Non-Fiscal & Regulatory Measures

Infrastructure, Power, RoW, and Regulatory Facilitation

Key Non-Fiscal Provisions (Clause 11)

CategoryRegulatory & Infrastructure Relief Provided
Haryana Building CodeSection 6.3(3)(iv) provides relaxed FAR of 500%, ground coverage up to 60%, and unrestricted building height.
Infrastructure StatusData Centres declared as an Infrastructure Industry vide Notification dated 22 Nov 2023.
Power SupplyContinuous dual-grid power networks provided; Data Centres declared as Energy Intensive Industry.
Water Supply24x7 dedicated industrial water supply provided for high-density cooling towers.
Connectivity & RoWRedundant last-mile fibre, Single Roof online Right of Way (RoW) clearance, Dial Before You Dig Policy.
Public Procurement PreferenceHARTRON empanelment; GoH departments to give 1st preference to empaneled DCs in Haryana.
HSIIDC Land ReservationHSIIDC to reserve dedicated plots in IMTs and Industrial Estates for Data Centre units.
Single Roof ClearancesPre-commencement approvals within 10 working days; Commencement approvals within 15 working days.
Essential ServicesDeclared Essential Service under Haryana Essential Services Maintenance Act (ESMA) 1974.
Property TaxProperty tax levied at par with standard industrial rates.
5. Document Checklist & Compliance

Requirements for Submitting Subsidy Claims

Mandatory Document Checklist for Claim Filings

S. No.Document RequiredTarget Head / Requirement
1Single Roof Portal Application FormSubmitted prior to commercial operations date (COD)
2Proof of Contracted Power Capacity (≥1 MW DC Unit / ≥20 MW Park)Contracted demand letter from UHVBN / DHVBN power utility
3Fixed Capital Investment (FCI) & ECE Audit ScheduleCertified by Chartered Accountant with invoice & payment ledgers
4Parivar Pehchan Patra (PPP) Verification RecordsMandatory proof for claiming Local Employment Generation Subsidy
5Net SGST Payment Cash Ledger ReceiptsRequired for annual OPEX reimbursement claim
6Wheeling / Transmission / Electricity Duty Payment ProofsSupporting documents for OPEX power cost reimbursement
7Green Building & Global DC Certifications (LEED / IGBC / BEE)For claiming certification CAPEX/OPEX reimbursements
8Town & Country Planning (TCP) License & Building Plan ApprovalsFor claiming FAR relief and Data Centre Park CAPEX tranches
6. Procedure

Step-by-Step Application Workflow

  1. 1Project Categorization: Determine contracted power capacity (Hyperscale >10 MW, Core 1–10 MW, Park ≥20 MW).
  2. 2File Pre-Commencement Application: Apply via HEPB Single Roof Clearance portal prior to starting commercial operations.
  3. 3Obtain Statutory Licenses: Secure TCP building plan approval (FAR 500%), fire NOC, dual grid power connection within 10–15 working days.
  4. 4Maintain Separate Books of Accounts: Expansions must obtain separate GST registration or maintain clear project ledgers.
  5. 5Verify Haryana Workforce: Onboard local employees via Parivar Pehchan Patra (PPP) portal.
  6. 6File CAPEX/OPEX Claim: Submit CA-certified FCI and ECE statements after COD to receive 10-year CAPEX instalments and 5-year OPEX support.
7. Official References & Gazette Mapping

Government Notifications, Statutory Citations & Legal References

The Haryana Data Centre Policy 2026 is published under the official authority of the Governor of Haryana and backed by statutory notifications and inter-departmental concurrences:

Reference / Citation HeadOfficial Gazette & Government Record Details
Primary Policy NotificationNo. 20/12/2026-4IB-1 dated 27th May, 2026; Department of Industries & Commerce, Government of Haryana.
Official Gazette PublicationHaryana Govt. Gazette (Extraordinary), No. 81-2026/Ext., Chandigarh, Wednesday, May 27, 2026 (Jyaistha 6, 1948 Saka).
Finance Department ConcurrenceU.O. No. 1/27/2026-3FD-III//2026/7008 dated 02.04.2026.
Cabinet ApprovalApproved by the Council of Ministers in its meeting held on 18th May, 2026.
Notification SignatoryAmit Kumar Agrawal, Commissioner & Secretary to Government Haryana, Industries & Commerce Department.
Infrastructure Industry StatusNotification No. 02/13/2023-41B-II dated 22nd November 2023.
Essential Services Maintenance (ESMA)Notification No. 47/1/2017-5 dated 12.07.2023 (declared under Haryana Essential Services Maintenance Act, 1974).
Transport Hub PermissibilityDepartment of Town & Country Planning Policy dated 19.03.2021 & amendment dated 14.12.2021.
Haryana Building Code ProvisionsSection 6.3(3)(iv) of the Haryana Building Code (500% FAR, 60% ground coverage, unrestricted height).
Local Employment VerificationParivar Pehchan Patra (PPP) system, Government of Haryana.
State Connectivity & RoW GuidelinesState Communication & Connectivity Infrastructure Policy, 2017.
Competent Interpretative AuthorityAdministrative Secretary, Department of Industries & Commerce, Haryana (Clause 8).
All applications, Right of Way (RoW) permissions, and Single Roof clearances are processed online through the Haryana Enterprise Promotion Board (HEPB) portal.