Factory Licence under the Factories Act, 1948 — Applicability, Documents, Inspection, Renewal and Boiler Registration

10 / 20 workers
With power / without power — Factories Act threshold
No threshold
Any hazardous process needs a licence
7 / 15 / 21 days
Rajasthan timeline: standard / non-hazardous without power / hazardous
1–10 years
Validity you can choose; fee scales with period
Share:
Chief Inspector of Factories and Boilers of the state (in Rajasthan, the Factories and Boilers Inspection Department through the Raj-FAB portal) · pan-India online filing by BookMyCALast verified against official guidelines on 5 September 2026.

Video Explanation & Insights

How to get a factory licence: documents, fees, inspection and renewal (Hindi)

2 videos on this topic

Overview

What the factory licence is, and who must take it

The Factories Act, 1948 is a central law administered by the state governments. It exists to protect the health, safety and welfare of the people who work in a factory — working hours, leave, ventilation, machine safety, fire precautions, hazardous chemicals — and it requires the occupier of a factory to obtain a licence from the state's Chief Inspector of Factories before running the premises. Every state operates its own portal and forms: Rajasthan through Raj-FAB, and Haryana, Uttar Pradesh and the others through their own labour or factories departments.

The occupier is the person with ultimate control over the factory — the proprietor, a partner, a director or the promoter named for the purpose — and the licence, the returns and the liability for non-compliance rest with that person. The Act applies once the premises cross a worker threshold or carry out a hazardous process, and increasingly a factory licence is also asked for in government tenders and by banks and buyers as proof that the unit is a lawful manufacturing establishment.

Applicability

SituationRuleNotes
Manufacturing with the aid of power10 or more workers on any day of the preceding twelve monthsContract and casual workers count
Manufacturing without power20 or more workersHandloom, hand-weaving and artisan units below this are outside the Act
Hazardous processLicence required regardless of the number of workersChemicals, gases, petroleum products, flammable and explosive materials, fireworks and the processes listed in the First Schedule
Boilers and pressure vesselsSeparate registration and certificate under the Boilers Act, 1923Annual inspection; the factory licence does not cover the boiler
MSME unitsSame worker test appliesUdyam registration does not exempt the unit
Construction sites with prefabricationPrefabrication activity on site can attract the ActCheck with the department before starting
Several states have notified higher thresholds through amendments (for example 20 with power and 40 without). The figures above are the Act's baseline, and Rajasthan applies them; we confirm the threshold notified in your state before advising.
Requirements

Three registrations before the licence

  • State business registration — in Rajasthan the Business Registration Number (BRN); other states have their own enterprise or shops-and-establishment registration.
  • Labour Identification Number (LIN) from the Shram Suvidha portal, which also links the unit's EPF and ESIC registrations.
  • Consent to Establish and Consent to Operate from the State Pollution Control Board — see our CTE / CTO page.

The factory licence application is filed only after these three exist, and the inspector will check the plant against the safety conditions before granting it. Operating a factory that meets the threshold without a licence attracts penalties and prosecution under the Act.

Documents

Documents for the application

Applicant

  • Occupier details: proprietor, partner or authorised director, with ID and photograph
  • MoA and AoA, or partnership deed / LLP agreement, PAN, GST
  • Board resolution or authority letter naming the occupier and manager
  • BRN, LIN and Pollution Board CTE / CTO

Premises

  • Ownership proof — sale deed, or lease deed / rent agreement
  • Electricity bill and sanctioned load letter
  • Site plan and building plan showing sections, exits, storage and machinery layout
  • Approved building plan or stability certificate where the state asks for it

Operations

  • List of machinery with horsepower
  • List of raw materials and finished products; hazardous substances declared
  • Process flow and number of workers, with worker list and Aadhaar copies
  • Safety measures: fire-fighting equipment, first aid, machine guarding, earthing; boiler registration if a boiler is installed
Process

Application to licence

  1. 1Step 1 — Prerequisites: BRN (or the state equivalent), LIN on Shram Suvidha and CTE / CTO from the Pollution Board are obtained.
  2. 2Step 2 — Application: filed online on the state portal (Raj-FAB in Rajasthan) with the plans, machinery list, worker details and safety declarations; fee paid according to horsepower and number of workers and the validity period chosen.
  3. 3Step 3 — Inspection: the Inspector of Factories visits the premises and checks fire-fighting equipment, first aid, machine guarding, earthing, ventilation, welfare facilities and hazardous storage; queries are answered.
  4. 4Step 4 — Grant: the inspector may approve, raise a query or reject; on approval the licence is downloaded from the portal.
  5. 5Step 5 — After the licence: statutory registers are maintained, dangerous occurrences and accidents are reported, the annual return is filed, any change of occupier, manager or expansion is notified, and renewal is filed before expiry.
Fees & timeline

Timeline, validity and renewal

ItemRajasthan (as explained in the video)Notes
Standard application7 daysAfter a complete application
Non-hazardous, without power15 days
Hazardous process21 daysInspection is more detailed
Validity1 to 10 years at the applicant's choiceFee is charged for the period chosen; many states allow up to five
RenewalBefore expiry, for 1 to 10 yearsLate renewal attracts a penalty fee
BoilerRegistration and annual certificate under the Boilers Act, 1923Separate application to the boiler inspector

Fees depend on the state's schedule: installed horsepower and the maximum number of workers set the slab, multiplied by the number of years applied for. Taking the licence for five or ten years at once is usually cheaper than renewing annually.

Example

A food-processing unit near Jaipur

A snack manufacturer installs 45 HP of machinery and employs 18 workers in a RIICO industrial area. It already has a BRN and Udyam registration; it obtains its LIN on Shram Suvidha in a week and its Consent to Operate from the Rajasthan State Pollution Control Board, then files on Raj-FAB with the site plan, machinery list and worker list, choosing a five-year validity. The inspector's visit notes that the fryer section has no fire extinguisher and the earthing certificate is missing; both are put in place within a week and the licence is granted. The unit's boiler is separately registered and certified under the Boilers Act.

Watch-outs

Common mistakes

  • Applying before the Pollution Board consent or the LIN exists — the application is returned.
  • Counting only permanent staff: contract, casual and seasonal workers all count towards the threshold.
  • No fire-fighting equipment, first-aid box or machine guards on the day of inspection.
  • Running a boiler without registration under the Boilers Act, 1923.
  • Letting the licence lapse and running on an expired licence — penalties and prosecution follow.
  • Not notifying a change of occupier or manager, or an expansion in horsepower or workers.
FAQs

Factory licence: questions we are asked

If you use power and have 10 or more workers, or 20 or more without power, yes — in the states that follow the Act's baseline thresholds. Any hazardous process needs a licence regardless of headcount.

The person with ultimate control of the factory: the proprietor, a partner, or a director named by the board. The occupier signs the application and carries the legal responsibility.

The state business registration (BRN in Rajasthan), the Labour Identification Number from Shram Suvidha, and Consent to Establish / Operate from the Pollution Control Board.

In Rajasthan, 7 days for a standard application, 15 days for a non-hazardous unit without power and 21 days for a hazardous unit, after a complete application and inspection.

You choose the period at filing — one year to several years (Rajasthan allows up to ten). The fee scales with the period, and renewal is filed before expiry.

No. A boiler needs its own registration and annual certificate under the Boilers Act, 1923 from the boiler inspector.

Fire-fighting equipment, first-aid arrangements, machine guarding and earthing, ventilation and lighting, welfare facilities and the handling of hazardous materials.

Yes. Every state has an online portal; we handle the prerequisites, the application, the inspection preparation and the renewal calendar pan-India.