
Chhattisgarh State Solar Energy Policy 2017–30
Policy Coverage at a Glance
The Chhattisgarh State Solar Energy Policy 2017–30 is administered by CREDA as nodal and single-window agency, under the overall supervision of an Empowered Committee chaired by the Chief Secretary. It sets out four categories of solar power plant, the commercial and regulatory terms on which each may sell or bank electricity, the industrial-policy and electricity-duty incentives available to a qualifying plant, and the land, timeline and operating-life conditions attached to those incentives. Clause 2 of the Policy states its period of operation as till 31 March 2030 or till the issuance of a new Solar Energy Policy, whichever is earlier.
Why the policy exists
The Introduction records that, in the context of increasing global awareness towards environmental conservation and climate change, it has become necessary to reduce the State's dependence on conventional coal-based sources and to make maximum use of non-conventional energy sources, among which solar energy occupies an important place. Keeping a balance between energy security and environmental conservation, promoting non-conventional sources is treated as a decisive strategy to eliminate dependence on fossil-based fuels in a planned manner and to bridge the gap between electricity demand and supply.
The Factual Case Recorded in the Introduction
| Head | What the gazette records |
|---|---|
| National context | MNRE announced the JNNSM in 2014 to meet energy needs using solar radiation available in India at average 5.5 kW/sq.m./day across average 300 sunny days. In 2014 GoI implemented financial assistance for 20,000 MW capacity under the Ultra Mega Solar Power Scheme; raised to 40,000 MW in 2017. |
| Nodal appointment | CREDA is appointed nodal agency to implement the MNRE scheme in the State and, with SECI, is making efforts for solar radiation use, including solar parks and ultra mega plants. |
| State potential | Because of high-intensity solar radiation, Chhattisgarh has unlimited possibility of being developed as India's major solar power production centre. Solar equipment manufacturing future is described as very bright. |
| Regulatory integration | Framed to incorporate CSERC regulations for grid-interactive decentralised renewable sources, together with industrial investment incentive provisions for solar power plants in the State's Industrial Policy. |
| Transmission readiness | CSPTCL has developed a strong transmission system with 400 kV, 220 kV and 132 kV lines in every area of the State, with capacity augmentation proposed for remote areas. |
Policy Objectives — Clause 1
- •Promote solar energy based power generation to meet demand, and for long-term environmental and economic benefits.
- •Promote private sector participation in solar power generation.
- •Create a favourable environment for development of solar generation capacities in the State.
- •Meet long-term energy needs and reduce thermal reliance.
- •Promote off-grid solar applications on a Stand Alone basis in remote and inaccessible areas.
- •Ensure clean energy access and decentralised production.
- •Create large-scale employment in solar production, manufacturing and ancillaries.
- •Effectively utilise fallow / non-agricultural unused land.
- •Develop skilled and semi-skilled human resources for this sector.
- •Encourage innovative projects related to solar power generation.
Who qualifies, and under which category
Eligibility of Project Developers — Clause 3
The following are eligible to set up solar power projects, whether for captive use and/or for sale of power, as per the Electricity Act 2003:
- •Any person.
- •Any registered company.
- •Central and State power generation and distribution companies.
- •Public and private sector solar power project developers — solar PV and solar thermal.
- •Manufacturing units of equipment related to solar projects, and ancillary industries.
Types of Solar Power Plants — Clause 5
| Category | Description |
|---|---|
| Category-I | Solar power plants to be set up under the competitive bidding tender invited by CSPDCL for sale of electricity. |
| Category-II | Power plants to be set up for captive use in the State, or for selling electricity under open access to consumers or licensees within or outside the State. |
| Category-III | Solar power plants to be set up under the REC–Solar Mechanism. |
| Category-IV | Solar power plants to be set up under the Jawaharlal Nehru National Solar Mission. |
Target Capacity by Category — Clause 6
| Category | Capacity Position |
|---|---|
| Category-I | Target in accordance with regulations notified from time to time by CSERC for RPO. No fixed MW figure is stated. |
| Category-II | Minimum capacity at a single location shall be 500 kW; maximum capacity per the National Solar Policy by MNRE. |
| Category-III | No limit on capacity under the REC (Solar) Mechanism. |
| Category-IV | Plants set up under the JNNSM are encouraged. No capacity figure is stated. |
Rooftop — Clause 4(d) and Clause 7
- •Grid connectivity will be provided to rooftop solar power plants of 1 kW, or of capacity more than 1 kW.
- •Solar power generation on building rooftops is treated as an important emerging area; pilot projects may be commenced with GoI support.
What the policy gives — exact provisions
A. Routes to Monetise Generation — Clause 4
| Route | Provision |
|---|---|
| Captive use or third-party open access | Connected project can be set up for self use or direct sale within or outside the State under open access. |
| REC (Solar) mechanism sale | Encourages producers to sell elsewhere under REC mechanism; CSPDCL can purchase under RPO at rates approved by Commission. |
| Sale of REC certificates | Producers permitted to sell REC certificates under CSERC/CERC regulations. |
| Rooftop grid connectivity | Connectivity provided to rooftop plants of 1 kW or more. |
B. Incentives Under the Industrial Policy — Clause 8
| Head | Provision |
|---|---|
| Industrial investment incentives | Solar generation plants set up during the policy period are eligible for Industrial Policy incentives, paid/adjusted by Commerce & Industry department. |
| Electricity duty exemption | 100% exemption on auxiliary consumption and captive consumption within the State, effective for projects set up till March 2030. |
| Land Bank allotment timeline | Must set up the plant within one year of obtaining possession of Land Bank land, or allotment is automatically cancelled. Concessional private land purchase requires same timeline, failing which concessions must be refunded with interest under Land Revenue Recovery Act. |
| Mandatory 25-year operation | Installed plant must be operated for 25 years from commercial production. Early closure triggers full repayment of all concessions received. |
C. Additional Incentives — Clause 9
| Head | Provision |
|---|---|
| Open access charges | Developer will pay the Open Access Charges and losses prescribed by CSERC / CERC for third-party sale outside the State. |
| Wheeling & transmission | Wheeling and transmission charges as per CSERC regulations. |
| Cross subsidy surcharge | Payable as per CSERC regulations for third-party sale within the State. |
| REC benefit for self use | Eligible for REC benefit on electricity fed into own dedicated grid for captive consumption. |
| RPO purchase by DISCOM | DISCOM will purchase for RPO compliance at rates determined through competitive open tender or pooled cost rates, at DISCOM's convenience. |
D. Banking — 100% banking facility, Clause 9(d)
Solar plants of the State are provided a 100% banking facility in every financial year, subject to verification of deposited units by CSPDCL, CSPDCL regulations for refund, and year-end disposal under CSERC rules. Banking charges vary by peak / off-peak period:
| Month | Banking charges in 'Off Peak' period | Banking charges in 'Peak' period |
|---|---|---|
| January | 2 per cent | 10 per cent |
| February to June | 5 per cent | 15 per cent |
| July to December | 2 per cent | 10 per cent |
E. Energy Accounting for Industrial Establishments — Clause 9(d)(v)
Industrial establishments in Category-II or Category-III purchasing from CSPDCL against contracted demand will have their energy accounting governed by CSERC (Intra State Availability Based Tariff and Deviation Settlement Mechanism) Regulations.
F. Permission to Sell — Clause 9(d)(vi)
Permitted to sell electricity within or outside the State, subject to orders and directives issued under the Electricity Act 2003 and CSERC regulations.
Beyond the tariff
A. Grid Connectivity and Power Connection — Clause 9(f)
- •Injection into the substation of the nearest CSPTCL / distribution licensee is permitted under the Grid Code.
- •Power line from the switch yard of the solar plant to the grid substation (interconnection point) will be established at the developer's expense.
- •Option to construct line under supervision (with fee) or own-supervision (no fee).
- •Must obtain confirmation of technical capacity availability from the transmission/distribution licensee before constructing.
- •Nodal utility must confirm capacity within 30 working days of application.
B. Land for a Grid-Connected Project — Clause 9(g)
- •Land allotment is made under Industrial Policy infrastructure development provisions.
- •Captive solar plants receive priority at the time of allocation of the Land Bank.
- •Model rehabilitation policy applies where the Government acquires private land.
- •Developer is solely responsible for obtaining statutory approvals and permissions.
C. Solar Parks — Clause 6(e)
State Government encourages development of solar parks with common infrastructure (land, water, roads). Setting up plants under private investment or PPP mode on a cost-sharing basis is encouraged.
D. Project Completion Timeline — Clause 10
Projects allotted must be completed within 36 months. Extensions may be granted by the Energy Department on request after progress review.
E. Prohibition on Fossil Fuel — Clause 11
Use of any fossil-based fuel (coal, gas, lignite, naphtha, wood) is strictly prohibited. Solar thermal plants installed within a unit's premises must be kept in physically separate premises from any pre-existing fossil-fuel plant.
What is needed, and the strings attached
Threshold Conditions
| Condition | Requirement |
|---|---|
| Eligible developer | Any person, company, utility, PV/thermal developer, or equipment manufacturer |
| Capacity limits | Category-II: Minimum 500 kW at a single site; Category-III: no capacity limit |
| Rooftop connectivity | Available for rooftop plants of 1 kW or above |
| Completion window | Within 36 months, extendable by Energy Department |
| Fossil-fuel prohibition | Strictly no fossil fuel; solar thermal must be physically separate from fossil units |
| Land Bank timeline | Must construct within one year of possession of land bank / concessional land |
| Concessions refund | Failure to construct in 1 year requires concessions refund; recoverable with interest |
| Operating life | 25-year mandatory operating life from commercial production date; early closure triggers concessions refund |
| Interconnection | Line constructed at developer's cost; own-supervision option avoids supervision fee |
| Capacity confirmation | Licensee must confirm capacity within 30 working days of application |
| DISCOM purchase | No mandatory purchase; CSPDCL purchases at its own convenience/tender rates |
Document Checklist — Grid-Connected Solar Power Project
| # | Document | Purpose / Linked Clause | Basis |
|---|---|---|---|
| 1 | Application to CREDA as nodal agency | Clause 12 & 13 — single window clearance authority | Confirmed |
| 2 | Developer constitution, PAN, GSTIN, authorisation | Eligible status under Clause 3 | Confirmed |
| 3 | Capacity certificate (min 500 kW single-site Category-II) | Clause 6(b) — Category-II minimum threshold | Confirmed |
| 4 | Category determination note (Cat I, II, III or IV) | Clause 5 — defines applicable open-access/banking rules | Confirmed |
| 5 | PPA with CSPDCL for Category-I project | Competitive bidding compliance | Confirmed |
| 6 | Land Bank allotment order / private title deed & diversion order | Clause 9(g) — land priority and infrastructure rules | Confirmed |
| 7 | CSPTCL/CSPDCL capacity availability confirmation | Clause 9(f) — due within 30 working days of application | Confirmed |
| 8 | Connectivity application, substation details, single line diagram | Grid Code compliance | Confirmed |
| 9 | Self-supervision election letter | Clause 9(f) — avoids the transmission utility's supervision fee | Confirmed |
| 10 | Open access permission application with charges undertaking | Clause 9(a) — third-party sale outside the State | Confirmed |
| 11 | Cross subsidy surcharge computation | Clause 9(c) — third-party sale within the State | Confirmed |
| 12 | Declaration of zero fossil-fuel usage | Clause 11 — express prohibition | Confirmed |
| 13 | Physically separate solar thermal site layout plan | Clause 11 — mandatory separate premises | Confirmed |
| 14 | Project schedule showing completion in 36 months | Clause 10 — time-bound project completion | Confirmed |
| 15 | CEIG / Electrical Inspector safety approval & commissioning cert | Fixes the commercial production date starting 25-year clock | Indicative |
| 16 | ABT metering and SLDC registration records | Required for deviation settlement accounting | Indicative |
| 17 | Consents to Establish and Operate from CECB | Statutory approvals responsibility | Indicative |
Document Checklist — Banking, REC, Land Bank & Incentives
| # | Document | Purpose / Linked Clause | Basis |
|---|---|---|---|
| 1 | CSPDCL competent authority banking verification | Clause 9(d)(i) — required each financial year | Confirmed |
| 2 | Month-wise drawal sheet mapped to Peak/Off-Peak | Clause 9(d)(iii) — Peak period (Feb-Jun) 15% banking charges | Confirmed |
| 3 | REC accreditation and registration file with injection logs | Clause 9(e) — REC benefits for self-use | Confirmed |
| 4 | Electricity duty exemption application | Clause 8(b) — auxiliary and captive consumption exemption | Confirmed |
| 5 | Industrial investment incentives application | Clause 8(a) — paid/adjusted by Commerce & Industries | Confirmed |
| 6 | Land Bank one-year construction undertaking | Clause 8(d) — construction within 12 months of possession | Confirmed |
| 7 | 25-year minimum operating life commitment | Clause 8(e) — early closure triggers concession refund | Confirmed |
Strings Attached
Concessions refund: Early closure before 25 years triggers refund of all concessions received. Delay in Land Bank or concessional private-land project execution beyond 1 year triggers automatic cancellation and recovery under Land Revenue Recovery Act.
Verification: Banked units must be verified each year by CSPDCL, and peak banking charges of 15% (Feb-June) are substantial. In case of discrepancy, the Hindi gazette text is authoritative.
Step-by-step application process
- 1Step 1 — Project categorization: Fix Category-I, II, III or IV based on sale route and 500 kW single-site limit.
- 2Step 2 — Land acquisition: Apply for Land Bank priority or purchase private land concessionally, registering the 1-year construction deadline.
- 3Step 3 — Interconnection capacity confirmation: Apply to transmission/distribution utility (30 working days confirmation window).
- 4Step 4 — CREDA Single Window clearance: Apply for statutory clearances, consents and allotment approvals.
- 5Step 5 — Supervision election: Submit self-supervision election to avoid utilities' fee.
- 6Step 6 — Open access and surcharge accounting: Apply for CSERC open access, wheeling, and cross subsidy surcharge approvals.
- 7Step 7 — REC registration: Register the project under CSERC/CERC REC guidelines.
- 8Step 8 — Project execution: Complete within 36 months, applying for department extensions if needed.
- 9Step 9 — Exemption filing: Apply for electricity duty exemption and industrial policy incentives.
- 10Step 10 — Banking operations: Execute yearly banking verifications with CSPDCL, tracking peak banking charges.
- 11Step 11 — 25-Year compliance: Operate continuously for 25 years from commercial production to avoid concession recovery.
Bodies governing the policy
| Body | Role |
|---|---|
| Nodal Agency — CREDA | Single window clearance, tenders, land bank identification, permissions, and right of way assistance. |
| Empowered Committee | Chaired by Chief Secretary. Monitors single window, resolves inter-departmental disputes and removes implementation difficulties. |
| Energy Department | Issues implementation guidelines separately, resolves policy difficulties, and oversees National Solar Mission alignment. |
| CSERC | Regulates RPO, REC registration, banking rules, wheeling/transmission charges, and ABT deviation settlement accounting. |
| Department of Commerce and Industry | Pays/adjusts industrial policy incentives for solar projects under Clause 8(a). |
Composition — Empowered Committee (9 members)
| Member | Position |
|---|---|
| Chief Secretary, Government of Chhattisgarh | Chairman |
| Secretary-in-charge, Finance Department | Member |
| Secretary-in-charge, Commerce and Industry Department | Member |
| Secretary-in-charge, Revenue Department | Member |
| Secretary-in-charge, Energy Department | Member |
| MD, CSPGCL | Member |
| MD, CSPTCL | Member |
| MD, CSPDCL | Member |
| CEO, CREDA | Member Secretary |
Key dates and durations
- •2014: MNRE JNNSM announced (20,000 MW target).
- •2017: JNNSM target raised to 40,000 MW.
- •09/11/2020: Order No. 1909 consolidates previous administrative steps.
- •04/11/2025: Energy Department issues Solar Policy 2017-30 consolidated under Order No. 2782/F 12/03/2017/13/2.
- •12/12/2025: Published in CG Rajpatra Part 1, No. 50 (pp. 1591-1612).
- •31/03/2030: Outer limit of Solar Policy operations (or issuance of a new Solar Energy Policy, whichever is earlier).
- •25 Years: Mandatory operating life from commercial production date (starts concessions refund protection).